SRTSmart Renovations ThailandRenovation and construction in Phuket

Phuket prices: 2016 vs 2026

"Everything used to be cheaper," everyone says. We checked what actually went up over ten years — labour, building materials or groceries. Official data and open sources only.

Construction tools

Labour: +33% in ten years

The minimum daily wage is the baseline for the cost of any work on a building site.

YearPhuket minimum wage, ฿ per day
2016300 (a single nationwide rate since 2013)
2017310
2025400
2026400

Since 2016, Phuket's minimum wage has risen by a third — from 300 to 400 baht a day. Skilled tradespeople earn above the minimum, so in a real quote the increase is felt even more.

Building materials: roughly +13%

Thailand's Ministry of Commerce publishes a construction materials price index with 2015 set at 100. At the end of 2025 the index stood at about 113 — meaning materials became roughly 13% more expensive on average over ten years. That's well below the rise in labour costs.

Materials don't rise evenly, though. In early 2016 cement and timber were getting cheaper while steel jumped 6.8% in a quarter (Thai Appraisal Foundation data). Today a 50 kg bag of Portland cement costs about ฿110–157 depending on the brand (October 2025). And overall construction costs rose 4.57% in 2026 year on year.

Groceries and living costs today

There are no verifiable prices for specific grocery items in Phuket shops for 2016 in open sources, and we won't make them up. So here are today's average prices — handy for checking against your own memories.

Item or serviceOctober 2026, ฿
Milk, 1 l57
Eggs, 1272
White rice, 1 kg52
Chicken fillet, 1 kg113
Water, 1.5 l18
Petrol, 1 l49
Meal at an inexpensive restaurant150
One-bedroom apartment outside the centre, per month15,600

Averages from Numbeo user data, updated 2 October 2026.

What this means for renovation

  • Labour is what's getting more expensive. Labour rose by a third in ten years, materials by about 13%. Cutting corners on tradespeople is a bad idea: cheap work usually means doing it twice.
  • Old quotes go stale. A quote made a couple of years ago almost certainly won't match reality today.
  • Fix the price in the contract. Scope, timeline and cost agreed before work starts protect you from price rises mid-project.

Need a quote at today's prices? We'll visit for free and cost out the renovation of your property. Message us on WhatsApp.

Sources